Build America, Buy America
Overview
The Build America, Buy America Act (BABA) requires that all iron and steel, construction materials, and manufactured products used in federally-funded infrastructure projects are produced in the United States. This requirement, known as the "Buy America Preference" (BAP), is detailed in the Infrastructure Investment and Jobs Act, Pub. L. 117-58 and 2 CFR 184.
BABA: What if I need a Waiver?
If seeking a waiver, Grantees should refer to the following information regarding the HUD Phased Implementation Schedule, General Waivers, and Specific Waivers to determine if and which waiver is needed. However, prior to seeking a waiver, grantees should determine if and how BABA applies to them and grantees should follow measures to maximize their compliance with BABA.
Important: HUD does not accept waiver requests submitted as PDF attachments or by email.
General Waivers and Timeline
HUD Phased Implementation Schedule
HUD has waived application of the BAP until the specific effective dates depending on the program and the product listed in HUD’s Phased Implementation Waiver. Please refer to HUD’s Phased Implementation Schedule below.
![[HUD’s Phased Implementation Schedule] [HUD’s Phased Implementation Schedule]](/sites/dfiles/Main/images/baba_apply_graphic2.jpg)
General Waivers
HUD has approved several general applicability waivers for specific public interest circumstances as summarized below. When the circumstances of any public interest general waiver are applicable to an infrastructure project, BABA’s domestic content procurement preference does not apply.
Small Grants | De Minimis | Exigent Circumstances |
|---|---|---|
BABA requirements do not apply to infrastructure projects whose total cost is equal to or less than the current Simplified Acquisition Threshold of $350,000. This waiver is currently in effect as of November 23, 2022. | BABA requirements do not apply for a De Minimis portion of an infrastructure project, meaning a cumulative total of no more than 5 percent of the total cost of the iron, steel, manufactured products, and construction materials, up to a maximum of $1 million. This waiver is currently in effect as of November 23, 2022. | This waiver applies when there is an urgent need by a grantee to immediately complete an infrastructure project because of a “exigent circumstances,” or a threat to life, safety, or property of residents and the community. This waiver is currently in effect as of November 23, 2022. |
The PDF waiver template is provided for reference purposes only to help applicants gather the information needed to complete the official waiver request in the HUD BABA Salesforce Portal.
All BABA waiver requests must be submitted through the HUD BABA Waiver Portal. PDF forms will not be processed as official submissions.
Additional information on HUD’s general waivers can be found in the drop-down menu below.
- Public Interest, General Applicability Waiver of Build America, Buy America Provisions as Applied to Pacific Island Territory Recipients of HUD Federal Financial Assistance: Final Notice (Effective as of November 15, 2023.)
- Public Interest De Minimis and Small Grants Waiver of Build America, Buy America Provisions as Applied to Recipients of HUD Federal Financial Assistance (Effective as of November 23, 2022.)
- Public Interest Waiver of Build America, Buy America Provisions for Exigent Circumstances as Applied to Certain Recipients of HUD Federal Financial Assistance (Effective as of November 23, 2022.)
- Public Interest Phased Implementation Waiver for FY 2022 and 2023 of Build America, Buy America Provisions as Applied to Recipients of HUD Federal Financial Assistance – establishes a phased-in implementation schedule for the BABA Buy America Preference (Effective for funds obligated by HUD on or after March 15, 2023 and expenditures of funds obligated by HUD between February 22, 2023 and March 15, 2023.)
- General Applicability Public Interest Waiver to Indian Tribes
- General Applicability Public Interest Waiver to Indian Tribes – Proposed Extension of Manufactured Products Waiver
(Waivers that Remain Applicable to Funds Obligated by HUD During Period of Applicability)
- Extension of Public Interest, General Applicability Tribal Consultation Waiver of Build America, Buy America Provisions as Applied to Tribal Recipients of HUD Federal Financial Assistance (Effective as of July 1, 2024.)
- Extension of Public Interest, General Applicability Waiver of Build America, Buy America Provisions as Applied to Tribal Recipients of HUD Federal Financial Assistance: Final Notice (Effective for funds obligated by HUD on or after May 23, 2024 and expenditures of funds obligated by HUD between May 14, 2023 and May 22, 2023.)
- Public Interest Phased Implementation Waiver of Build America, Buy America Provisions as Applied to Recipients of HUD Federal Financial Assistance (Applicable to funds obligated by HUD from November 23, 2022 to February 21, 2023 and expenditures of funds obligated by HUD between November 15, 2022 and November 23, 2022.)
- General Applicability Waiver of Build America, Buy America Provisions as Applied to Recipients of HUD Federal Financial Assistance (Applicable to funds obligated by HUD on or before November 14, 2022)
- General Applicability Waiver of Build America, Buy America Provisions as Applied to Tribal Recipients of HUD Federal Financial Assistance (Effective for funds obligated by HUD before May 14, 2023)
- Extension of Public Interest, General Applicability Tribal Consultation Waiver of Build America, Buy America Provisions as Applied to Tribal Recipients of HUD Federal Financial Assistance (Proposed May 10, 2024)
- Extension of Public Interest, General Applicability Waiver of Build America, Buy America Provisions as Applied to Tribal Recipients of HUD Federal Financial Assistance (Proposed April 7, 2023; Public comment extended to May 8, 2023 via Extension of Public Interest, General Applicability Waiver of Build America, Buy America Provisions as Applied to Tribal Recipients of HUD Federal Financial Assistance: Extension of Public Comment Period.
- Public Interest Phased Implementation Waiver for FY2022 and 2023 of Build America, Buy America Provisions as Applied to Recipients of HUD Federal Financial Assistance (Proposed February 15, 2023); also available in the Federal Register here.
- Public Interest Phased Implementation Waiver of Build America, Buy America Provisions as Applied to Recipients of HUD Federal Financial Assistance (Proposed November 3, 2022); also available in the Federal Register here. **Comment period extended until November 21, 2022**
- Public Interest De Minimis, Small Grants, and Minor Components Waiver of Build America, Buy America Provisions as Applied to Certain Recipients of HUD Federal Financial Assistance (Proposed October 31, 2022); also available in the Federal Register here.
- Public Interest Exigent Circumstances Waiver of Build America, Buy America Provisions as Applied to Certain Recipients of HUD Federal Financial Assistance (Proposed October 31, 2022); also available in the Federal Register here.
- General Applicability Waiver of Build America, Buy America Provisions as Applied to Recipients of HUD Federal Financial Assistance (Proposed April 29, 2022)
- General Applicability Waiver of Build America, Buy America Provisions as Applied to Tribal Recipients of HUD Federal Financial Assistance (Proposed April 29, 2022)
Specific Waivers
- Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Hershey Hall Affordable Apartments Project for Fire Alarm and Life Safety System, Electronic Components and Electrical Panelboards (HUD Waiver #W-0000228)
- Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Timber Ridge Affordable Housing Project for Nine Manufactured Products (HUD Waiver #W-0000183)
- Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Housing Hope Affordable Housing Project for Ductless Split-System Heat Pump Units, Elevators, and a Fire Alarm System (HUD Waiver #W-0000395)
- Solicitation of Public Comment for Project-Specific Build America, Buy America Nonavailability Waiver Proposal
- Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Wagoner on the Creek Affordable Housing Project for Door Hardware, Electrical, Elevator, Fire Alarm, HVAC, Lighting, and Plumbing (HUD Waiver #W-0000166)
- Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Camino De Salud Affordable Housing Project for Ductless Mini Split Heat Pumps (HUD Waiver #W-0000238)
- Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Simpson Crossings Affordable Housing Project for HVAC, Plumbing, Electronic Door Locks, and Lighting and Wiring (HUD Waiver #W-0000230)
- Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the City of Fort Collins for the Windtrail Park Apartments Rehabilitation Project for multiple products (W-0000203 through W-0000210)
- Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Poverello Center Affordable Housing Project for a Plumbing Materials (HUD Waiver #W-0000162)
- Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Topeka Senior Villas Affordable Housing Project for Vertical Heat Pumps (HUD Waiver #W-0000182)
- Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Columbia Renaissance Square III Affordable Housing Development for Door Hardware (Deadbolts, Lever Sets, Closers, Stops, Viewer, and Panic Exit Device) (HUD Waiver #W-0000382)
- Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Saddlehorn Apartments for Mini Split Heat Pumps and Vertical Terminal Air Conditioners (HUD Waiver #W-0000290)
- Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Talon Townhomes Affordable Housing Project for HVAC Equipment (HUD Waiver #W-0000380)
- Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the City of Chico 25 Via La Paz Project for HVAC Equipment (HUD Waiver #W-0000369)
- Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Tendick Street Affordable Housing Project for HVAC Equipment and a CCTV Surveillance System (HUD Waiver #W-0000235)
- Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Westpark Redevelopment Project for Variable Refrigerant Flow Heat Pump Systems (HUD Waiver #W-0000077)
- Project Specific Non-Availability Waiver Build America Buy America Product Waiver: Heat Pump System
- Solicitation of Public Comment for Project-Specific Build America, Buy America Nonavailability Waiver Proposal (Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Saxman Affordable Housing Project for Mini-Split Heat Pumps)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Columbia Renaissance Square III Affordable Housing Development for Water Cooler, Supply Lines, Floor Sink, Circulator Pump, RPZ, and ADA Signaling (HUD Waiver #W-0000351)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Tendick Street Apartments for Fire Alarm Equipment (HUD Waiver #W-0000321)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act Requirements to the Columbia Renaissance Square III Affordable Housing Development for Sub Water Meters, Bath Accessories, Exhaust Fans, HVAC Equipment, and Smart Locks (HUD Waiver #W-0000157)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the 331 Cumberland Avenue and Pettengill Pines Affordable Housing Projects for HVAC Equipment (HUD Waiver #W-0000095)
- Final Project Specific Non-Availability Waiver of Build America Buy America (BABA) Product Waiver: Heat Pump System
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the St. Cecilia Senior Housing Project for Heat Pumps (HUD Waiver #W-0000292)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the MacArthur Senior Flats Affordable Housing Project for Heat Pumps and Fire Alarm Devices (HUD Waiver #W-0000240)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Bretz Court Senior Affordable Housing Project for Heat Pumps (HUD Waiver #W-0000295)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Grove Affordable Housing Project for Surface Mounted Downlights (HUD Waiver #W-0000155)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Judith Ann, Maxine, and Velenna Jo Affordable Housing Projects for HVAC Materials, LED Light Fixtures, and Fire Alarm System (HUD Waiver #W-0000150)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the 100 Flanders Street Affordable Housing Project for a Variable Refrigerant Flow System (HUD Waiver #W-0000173)
- Final Project-Specific Public Interest Waiver of Build America Buy America Act (BABA) Requirements for the New City Plaza Apartments (HUD Waiver #W-0000039)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Stables Affordable Housing Project for HVAC Equipment (HUD Waiver #W-0000102)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Grove at Cottonwood Affordable Housing Project for HVAC Equipment (HUD Waiver #W-0000107)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the 6104 Roosevelt Road Affordable Housing Project for a Variable Refrigerant Flow System (HUD Waiver #W-0000127)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Grove at Cottonwood Affordable Housing Project for an Access Control System, a Fire Alarm System, and Plumbing Equipment (HUD Waiver #W-0000105)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Riverside/Imani Village Phase V Affordable Housing Project for Ductless Split Systems (HUD Waiver #W-0000131)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Stables Affordable Housing Project for Carpentry Hardware, Elevators, Lighting and Electrical Supplies, Fire Suppression System, and Plumbing Items (HUD Waiver #W-0000099)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Anchorage South Affordable Housing Project for HVAC Equipment (HUD Waiver #W-0000132)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements for the Maine School Administrative District 54 Margaret Chase Smith Community School and Early Childhood Center
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Poverello Center Veterans Housing Project for Variable Refrigerant Flow System (HUD Waiver #W-0000088)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Saxman Affordable Housing Project for Mini-Split Heat Pumps (HUD Waiver #W-0000041)
- Final Nonavailability Waiver of Build America Buy America Act Provisions for Fire Alarm Equipment Used in the Ranleagh Court and Waverly Winds Affordable Housing Projects in Howard County, Maryland
- Final Nonavailability Waiver of Build America Buy America Act Provisions for HVAC Equipment Used in the Ranleagh Court and Waverly Winds Affordable Housing Projects in Howard County, Maryland
- Final Nonavailability Waiver of Build America Buy America Act Provisions for Braided Dishwasher Supply and Trap Seals Used in the Ranleagh Court and Waverly Winds Affordable Housing Projects in Howard County, Maryland
- Final Nonavailability Waiver of Build America Buy America Act Provisions for Door Hardware Used in the Ranleagh Court and Waverly Winds Affordable Housing Projects in Howard County, Maryland
- Final Nonavailability Waiver of Build America Buy America Act Provisions for Plumbing Fixtures and Accessories Used in the Ranleagh Court and Waverly Winds Affordable Housing Projects in Howard County, Maryland
- Final Nonavailability Waiver of Build America Buy America Act Provisions for Water Flow Devices Used in the Ranleagh Court and Waverly Winds Affordable Housing Projects in Howard County, Maryland
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Illinois Housing Development Authority (IHDA) for a Variable Refrigerant Flow (VRF) System
- Final Nonavailability Waiver of Build America Buy America Act Provisions for Select Iron and Steel Products Used in the Riverplace Park Playground project, City of Port St. Lucie, Florida
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Voyager’s Village Affordable Housing Project for Circuit Breakers (HUD Waiver #W-0000040)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Hilltop Manor Apartments Affordable Housing Project for Mini-Split Heat Pumps (HUD Waiver #W-0000059)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Goldfinch Lofts Affordable Housing Project for Prefabricated Windows (HUD Waiver #W-0000084)
- Under Evaluation: Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Goldfinch Lofts Affordable Housing Project for an Elevator (HUD Waiver #W-0000085)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Goldfinch Lofts Affordable Housing Project for Ductless Mini-Split Heat Pumps (HUD Waiver #W-0000091)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Green Park Affordable Housing Rehabilitation Project for Smart Deadbolts and Passage Levers (HUD Waiver #W-0000046)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Green Park Apartments Affordable Housing Rehabilitation Project for Bathroom Fan Motors (HUD Waiver #W-0000047)
- Final Project-Specific Nonavailability Waiver of Build America Buy America Act (BABA) Requirements to the Green Park Affordable Housing Rehabilitation Project for Plumbing Equipment (HUD Waiver #W-0000048)
In addition to HUD’s general waivers, HUD may also request specific waivers from the BAP for covered FFA on a limited, case-by-case basis, after consultation and review with the MIAO at OMB.
Agencies may apply to waive the domestic content procurement preference if:
- Requiring the use of the American made product would be inconsistent with the public interest (Public Interest Waiver);
- The product you need is not produced in the United States in sufficient quantities or of a satisfactory quality (Non-Availability Waiver); or,
- The inclusion of the product produced in the United States will increase the cost of the overall project by more than 25 percent (Unreasonable Cost Waiver).
See below for additional descriptions of waiver categories:
Public Interest Waiver
This waiver is granted if requiring the use of the American made product would be inconsistent with the public interest.
In their waiver application, Grantees should:
- Explain how waiving the BABA requirement for this project or product serves the public interest.
- Demonstrate definite impacts on the community if specific items, products, or materials are not utilized in an infrastructure project.
Non-Availability Waiver
This waiver is granted if the product needed is not produced in the United States in sufficient quantities or of a satisfactory quality.
In their waiver application, Grantees should:
- Demonstrate that they have conducted market research and adequately considered alternate items that meet the definition of Made in America.
- Describe the due diligence performed, including information, quotes, and/or responses from manufacturers, distributors, or suppliers.
Unreasonable Cost Waiver
This waiver is granted if the inclusion of the product produced in the United States will increase the cost of the overall project by more than 25 percent.
In their waiver application, Grantees should:
- Demonstrate that BABA compliance increases total project cost by more than 25%.
- Determine the additional cost of BABA compliant products.
- Determine the dollar amount to be waived.
- Demonstrate that no domestic alternatives are available within the project budget.
How do I apply for a Specific Waiver?
HUD reviews waivers before they are posted to the Federal Register for public comment and sent to the Made In America Office (MIAO) for approval. In general, the BABA Waiver Process follows these steps for approval:
- Contact the HUD Program Office for BABA technical assistance as needed.
- Prepare a waiver application with the information required by the MIAO. Please note that only the direct HUD recipients (grantees and public housing authorities) may submit the waiver application. HUD direct recipients are strongly encouraged to coordinate with their subgrantee(s) or subcontractor(s) to collect the necessary information for a waiver application using the PDF form here.
- Submit a waiver application with all necessary information to HUD’s BABA Waiver Submission Site. Please contact [email protected] with any waiver-specific questions or technical difficulties. You may refer to this training video for how to submit a waiver. We recommend that you prepare to input all your waiver information in one session since there is no mechanism to save an unfinished application.
- Provide additional information as requested by HUD during the review process to proceed with public comment in the Federal Register, and final approval by MIAO.
- If approved, the waiver is posted on MadeInAmerica.gov
Contacting HUD About BABA
If your BABA inquiry relates directly to a specific grant or project, please direct your questions to the HUD office that administers your grant or program and copy [email protected].
- Community Planning and Development (CPD) – CDBG, HOME, CoC, ESG, HTF,CPF (EDI), RHP, Section 108, SHOP, PRO Housing, PRICE , CoC Builds, VHRMP, SHOP and related programs: [email protected]
- Public and Indian Housing (PIH) – Choice Neighborhoods, Public Housing Operating and Capital Fund, and MTW programs: [email protected]
- Office of Native American Programs (ONAP) – IHBG, ICDBG, and NHHBG programs: [email protected]
- Office of Lead Hazard Control and Healthy Homes (OLHCHH) – Lead Hazard Reduction and Healthy Homes programs: [email protected]
- Multifamily Housing (MFH) – GRRP, Section 202, and Section 811 programs: [email protected]
General Guidance: Please contact [email protected] directly for general questions or if you are unsure of your specific HUD office. When submitting an inquiry, if available, please provide any available details about your project, including the funding source, to assist us in responding efficiently. Additional information regarding BABA requirements, implementation guidance, and resources are available on HUD Exchange.